Final Plans

Below are the final plans submitted to Mosman Park Council for approval. Many revisions have been made compared with the earlier Concept Plan.
  1. the size of most rooms has been reduced.
  2. the second bathroom on the ground-floor has been removed and the en-suite bathroom enlarged slightly.
  3. the layout of the upper-storey has been completely rearranged.
  4. the front-elevation has been altered to better suit our taste.
Steps 1. and 2. lowered the estimated building costs by approximately $30,000.

We also included with our submission to Council comments from our neighbours regarding overlooking windows and the balcony.

Council approved the plans in April 2008 with one proviso - that a darker roof colour (than "Surf Mist") be used - we will use "Dune".